Helicopter Services

Wilson continues to help pioneer safe and efficient helicopter operations in the electric utility construction industry, including  participation in the development of standardized safe practices and procedures in national and international safety guidelines. Our extensive fleet of helicopters and veteran pilots can complete complex jobs safely and efficiently where others can’t.

Southern California Edison Company

TLRR Bulk Power 220-500kV Project Work Package 1
Wilson reconductored 110 miles of 500kV Bluebird conductor for Southern California Edison Company (SCE).

Video: 230kV Transmission Line

Blue Lake to Gresham 230kV Transmission Line, OR
Wilson crews installed a new 230kV transmission line near Portland, Oregon.

Bonneville Power Administration

Spacer-Damper Replacement Project; OR, WA, MT
Since 2006, Wilson has been conducting spacer-damper replacements on several Bonneville Power Administration 500kV transmission lines. The efforts have taken crews throughout Oregon, Washington, and Montana. Work has been performed…

Southern California Edison

Pastoria – Pardee 230kV Transmission Line Construction, CA
Wilson rebuilt approximately four miles of 230kV lattice steel transmission line, one of the oldest in the West, which had become prone to ice damage. The upgrade involved raising the…