The project consisted of approximately 8,000 feet of 630mm2 345kV XLPE copper cable, 15 GIS terminators and 15 open-air terminators. Project requirements included designing a GIS pit to incorporate five circuits, with cables installed at different times over a two-year period.
Plant Developer
Center Substation 345kV Solid Dielectric Interconnects, TX
View the embedded image gallery online at:
https://www.wilsonconst.com/services/underground-construction/item/46-plant-developer-center-substation-345kv-solid-dielectric-interconnects-tx#sigProId226cbb9c1d
https://www.wilsonconst.com/services/underground-construction/item/46-plant-developer-center-substation-345kv-solid-dielectric-interconnects-tx#sigProId226cbb9c1d
This project included the design, procurement, and construction of the underground duct bank, cable system and GIS pits for five 345kV solid dielectric cable interconnects from the Independent Power Producer plant to the GIS equipment in Deer Park, Texas.